Planning for uncertainty
Is resource planning in architecture really that different?Are we as “special” as we like to think we are?
This text started as notes I wrote in 2022 for a university talk that I never ended up giving. Four years later I picked it up again and revised it in light of what I have learned since.
Architects like to think our profession is quite particular. But how particular is it, really? What makes the way we work different from other professional services firms? And if those differences exist, why is it so hard to find resource planning software that fits them?
Imagine an architecture project we have been working on for two years. The team knows the building, the client, the technical problems and the reasons behind hundreds of design decisions.
Suddenly, the project stops.
Maybe a planning approval is delayed, the funding becomes uncertain or the client needs to rethink the brief. Six months later, the project starts again. Ideally we would get the same team back and pick up where we left off. But those people are now working on other projects, with their own commitments and deadlines.
Meanwhile, another project that looked safe has been postponed, a new commission needs a team almost immediately, and a third needs urgent reinforcements because it has to take on a major redesign without moving the delivery date.
None of this is especially unusual in an architecture office. It is part of our daily work.
Maybe we are not as special as we like to think, even if we are certainly “the coolest people on site”. Many of these problems exist in other sectors too. But long projects, contracts split into phases, decisions made by others and teams that build up knowledge over years make our planning problems quite particular.
So the question is whether conventional resource planning models describe our reality properly.
Uncertainty is part of the business
Architecture projects rarely follow a predictable sequence from commission to completion.
Sometimes we start working before a contract is even signed. Larger commissions are usually contracted in phases, with no guarantee that the next ones will go ahead. Projects can be put on hold for months, even years, because of permits, political decisions, economic conditions or a change in the client’s strategy.
Even when a project keeps going, its scope and schedule can change a lot. Redesigns, new requirements and unexpected technical problems can completely change what resources we need. There are periods of frantic activity, followed by others when almost nothing moves.
Certainty is also not necessarily a property of the project as a whole. One phase can be fully contracted while the next one is still open. A project can be active today and still tell us nothing about the workload six months from now.
To plan, we need to show not only the work we expect, but also how far we can really count on it.
And this uncertainty is not an exception that we can fix by improving our procedures. It is part of the business itself.
Two dimensions for one position
In conventional planning models, the main question is usually whether a position is assigned to a person or not.
But there is another question that matters just as much: how certain is it that we need that position at all?
These are two independent dimensions: certainty and assignment.
Combining them gives four possible situations:
| Assigned | Unassigned | |
|---|---|---|
| Certain | Confirmed position with a person assigned | Confirmed need, still to be filled |
| Uncertain | Position still uncertain, with a person pencilled in | Possible need, nobody assigned |
All four are common in our daily reality.
A certain position with nobody assigned is a staffing need we have to solve. An uncertain position with someone assigned is a possible future commitment that can limit that person’s availability, even though the project phase is not yet confirmed.
Take an architect we want to keep on a project for the next phase, which has not been contracted yet. We do not want to lose them for that team, but we cannot treat them as busy with the same certainty as if the phase were confirmed.
If our planning does not tell these situations apart, we will end up overestimating or underestimating the capacity we have.
Separating how certain a position is from whether it is assigned lets us tell apart committed workload, possible demand and provisional staffing decisions.
Above all, it shows how far we can trust our occupancy forecasts, because in six months we may find ourselves with too many people, too few, or simply not knowing yet what will happen.
We plan teams, not just capacity
The people who work in an architecture office are not interchangeable units of production.
Over time, teams build up knowledge that is hard to document in full: design decisions, technical constraints, what the client expects, the history of coordination and the many compromises that shape a building.
Keeping teams together means keeping that knowledge. Replacing one person with another of equal qualification does not mean we can keep working with the same efficiency.
At the same time, every project needs its own mix of skills.
Architectural design, technical development, construction experience, project management, digital skills or knowledge of local regulations may all be needed, but not in the same proportions or at the same moments.
We do not need the same kind of team during Concept Design as during Design Development or when preparing the Construction Documents.
Planning has to balance needs that often pull against each other: keeping teams together, combining the right skills, responding to swings in workload and keeping enough flexibility to deal with surprises.
There is one more dimension that is often forgotten: professional development.
Assigning someone to a project can be a chance to gain experience, build new skills or prepare for more responsibility. But that person can also see it as being pigeonholed, stuck or even frustrated.
Instead of automatically filling a position with the first person who is free, we need to be able to look at several candidates and discuss who is the best fit, taking into account their experience, their skills, their current commitments and their professional interests.
The difficulty is that project needs, people’s availability and their personal interests do not always line up. We may have the ideal candidate for a position, but need them urgently on another project. Or we may have someone free who would rather develop other skills. Planning also means resolving these conflicts, even when there is no solution that works for everyone.
And through all of this, software should support the process, not dictate it.
The illusion of precision
Many resource planning systems are built around hours, task assignments and decimal-level detail.
These measures can work for some professional services, where the jobs are short, repetitive, comparable and/or billed directly by the hour.
But are they always the right way to plan work in architecture?
Think of an architect who will work full time on one project for four or five months, until a technical design phase is delivered.
Also, most architecture contracts are set as lump-sum fees tied to phases and deliverables, not billed hour by hour.
Trying to split that person’s capacity between several projects in advance, and “in hours”, can produce a level of detail that is unreliable and of little use… 921 hours?? Or 5 months at 100%?
We can describe that need as roughly 921 hours of work. Mathematically, that is correct. But what extra information does that number give us to decide who goes where?
Here, knowing that we need one person at 100 % (1 FTE) for five months describes the commitment we want to plan much better. The exact hours will depend on the calendar, the deadlines, what goes wrong and how the project develops.
That information can be enough to make assignment decisions, without having to work out how many hours exactly someone will work each day or each week.
Architecture projects run for months or years. Their workloads go up and down. Design reviews, deadlines, redesigns and coordination needs create peaks and troughs that are hard to predict precisely, and some flexibility is needed too.
Precision belongs in the record of hours actually worked, in the timesheets. That gives us exact staff costs for each project. Planning precision, on the other hand, has to match how reliable our information is. Talking about hours makes little sense in capacity forecasts six months or a year out. Total precision about what has happened; rigorous planning, with tolerances, about what is ahead.
Let us avoid precision that only looks precise but is really uncertain, and that, far from helping, ends up working against us.
Two views of the same reality
We should be able to look at resource planning from two complementary angles.
From the whole portfolio of projects, we need to understand future demand. How many FTE will we need in six months? And in a year? How much of that demand comes from confirmed projects or phases? How much is still uncertain? Where do we have needs we have not yet filled?
From the people’s side, we need to know their availability, their commitments, their experience and their skills. And how we are spreading different kinds of talent across the teams. These are not two separate plans.
A project lead needs to know whether they can count on the right team for the next phase. A resource manager needs to understand what that decision means for other projects and for the people involved.
Across all projects, we should be able to see where certain experience is concentrated, which teams depend too much on certain people, and which skills we will need to develop or hire in the future.
We should also be able to see the consequences of changes before they happen.
If a project is delayed by three months, what happens to the people we had lined up for it? Can we use them on another project in the meantime? What will it cost to get them back when the first one restarts?
If a delivery is brought forward or a major redesign comes up, where can we find the extra capacity without hurting the other projects?
These are decisions we have to make all the time. And to make them we need one view of projects and people together, not just a list of individual assignments.
When software dictates the process
Commercial resource planning tools offer ever more sophisticated features. But many start from assumptions that do not always match how architecture is practised.
The problem appears when we want to hold a person provisionally for a phase that is still uncertain, consider alternative candidates, and see at the same time what would happen to the other projects if that phase is confirmed. Many tools can handle some of these situations, but fitting them into one coherent plan may need parallel procedures, complicated setups or awkward workarounds.
So: should we adapt our processes to the structure of a software product, or should our tools reflect how we actually work?
Standardisation makes sense for many business functions. But resource planning is closely tied to the particulars of what we do.
We often find commercial tools with dashboards in a thousand colours, fancy charts and indicators calculated to the third decimal. Very impressive, except for one detail: much of the information those forecasts are built on is, by definition, uncertain.
And it makes little sense to put more effort into sharpening a forecast than into understanding how far we can trust it.
So what do we actually need?
After all this, our needs do not look especially strange.
We want to tell certain positions from uncertain ones, whether or not they have a person assigned. We want to consider several candidates for a position before deciding who fits best. We need to know our people’s skills and experience, but also take into account their interests and their growth in the company.
We want to plan in units that make sense for our work: weeks, months and percentages of a full-time workload (FTE).
And we need to be able to look at that plan both from the projects and from the people, and see what a decision means for the rest of the organisation.
None of this removes the uncertainty. A project will still stop unexpectedly, another will need more people than planned, and sometimes we will have to reorganise several teams to deal with an emergency. That is not going to change.
What we can change is how we represent that reality and the information we use to make decisions.